AI Summary. Inflation-adjusted US public transit bus prices show almost no trend by bus type, with electric buses holding slightly above $1m, hybrids around $850,000, and diesels near $500,000 — the same level as in 1983.

Date Posted:
Is Database:
Database

In the US, prices of private vehicles have dropped 40% (quality adjusted) since 1995, but costs of US-produced transit buses have remained flat, exceeding foreign prices. A duopoly in manufacturing, customization, and “Buy America” rules keep costs high.

Have inflation-adjusted public transit bus prices changed over time?

Core argument: The median inflation-adjusted price of a US electric transit bus has hovered slightly above $1 million across the period covered, showing almost no trend despite rapid improvements in electric vehicle technology.

Our data [shows] US buses are expensive. The prices are corrected for inflation to 2024 dollars. There is almost no trend in any of the median prices within bus type. The median price of an electric bus hovers slightly above $1 million through-out this period, which may be surprising given the rapid improvements in electric vehicle technology. (A counterargument is that the improvements in the technology led to rising prices, but the same does not hold for heavy-duty electric vehicles.) The cost of a hybrid bus rose until 2015 but has remained relatively constant since then at about $850,000. Diesel buses hover around $500,000, just as in 1983, when New York bought 325 buses from General Motors.

Takeaways by Macro Roundup® AI

  1. The median inflation-adjusted price of a US electric transit bus has hovered slightly above $1 million across the period covered, showing almost no trend despite rapid improvements in electric vehicle technology.
  2. Median US diesel bus prices, in 2024 dollars, sit around $500,000 — the same level as in 1983, when New York bought 325 buses from General Motors.
  3. Median hybrid bus prices rose until 2015 and have remained relatively constant since then at about $850,000.

AI Summary. The US cannot fill about a third of the more than 400,000 new engineering roles created each year, and the UK faces a shortfall of 1 million engineering jobs as 20% of its engineers retire. Shortages of skilled workers raise costs and lengthen timelines for building electricity grids and data centers.

Date Posted:
Is Database:
Database

Aging populations and anti-immigration rhetoric in rich countries are forcing companies building electricity infrastructure to find creative solutions to meet surging demand. The US is unable to fill a third of its 400k+ new annual engineering roles.

Are engineer shortages raising costs and delaying grid and data center construction?

Core argument: The US cannot fill about a third of the more than 400,000 new engineering roles created each year, while 20% of the UK's engineers will retire by 2030, leaving a shortfall of 1 million jobs.

How do you get more labor? “You either birth them or you import them,” says Zeke Hernandez, professor at the Wharton School of the University of Pennsylvania. “But in an environment of declining birth rates, increasing retirements and now a restrictive immigration regime, shortages become quite severe.” The US is already unable to fill about a third of its more than 400,000 new engineer roles created each year. The UK will see 20% of its engineers retire by 2030 — leaving a shortfall of 1 million jobs. Skilled worker shortages lead to higher costs and longer timelines to build much-needed infrastructure, such as electricity grids. This is a problem for the US and Europe, which are seeing a surge in demand for power thanks to electric cars, heat pumps and massive data centers. The severe shortage of skilled workers is slowing progress towards electrifying everything. Some data center builders in the US are delaying new work, while others are having to plan projects two years in advance instead of six months.

Takeaways by Macro Roundup® AI

  1. The US cannot fill about a third of the more than 400,000 new engineering roles created each year, while 20% of the UK's engineers will retire by 2030, leaving a shortfall of 1 million jobs.
  2. Wharton professor Zeke Hernandez argues labor comes only from births or immigration, and that declining birth rates, rising retirements and a restrictive immigration regime make shortages quite severe.
  3. Skilled worker shortages raise costs and lengthen timelines for infrastructure such as electricity grids, with some US data center builders delaying new work and others planning projects two years ahead instead of six months.

AI Summary. State audits and independent evaluations of corporate tax incentive programs have found poor targeting, weak oversight, and excessive costs that harmed rather than benefited local governments. Examples include $5.5bn in New York tax credits for a Micron facility and up to $1.75bn in Michigan incentives for a Ford electric vehicle plant.

Date Posted:
Is Database:
Database

.@iamstevenpedigo and @NateMJensen write that the CHIPS Act, which requires state and local subsidies to access federal dollars, has thus far been gamed by corporations to the detriment of state and local governments.

Do corporate tax incentives harm the local governments that offer them?

Core argument: New York offered Micron $5.5 billion in tax credits over the life of the project, costing local and state governments upward of $95 million annually, far more than they are likely to gain from hosting the new facilities.

Offering tax breaks and other incentives to corporations has been proved to be one of the least effective ways for localities and states to grow their economies. State audits and independent evaluations of these programs found poor targeting of incentives, weak oversight and excessive costs that harmed rather than benefited local governments. The CHIPS Act and the Inflation Reduction Act are threatening to give [unproductive tax incentives] an enormous infusion of steroids. Micron chose to build in upstate New York [after] the state offered a staggering $5.5 billion in tax credits over the life of the project … costing local and state governments upward of $95 million annually, far more than they are likely to gain from hosting the new facilities.  In February, Ford agreed to build its new electric vehicle plant in Michigan, but only after extracting a promise of as much $1.75 billion in state and local incentives...enough money to pay all the new workers’ salaries for around 15 years.

Takeaways by Macro Roundup® AI

  1. New York offered Micron $5.5 billion in tax credits over the life of the project, costing local and state governments upward of $95 million annually, far more than they are likely to gain from hosting the new facilities.
  2. Ford agreed to build its new electric vehicle plant in Michigan only after extracting a promise of as much as $1.75 billion in state and local incentives, enough to pay all the new workers' salaries for around 15 years.
  3. State audits and independent evaluations of corporate tax-break programs found poor targeting of incentives, weak oversight and excessive costs that harmed rather than benefited local governments, with the CHIPS Act and the Inflation Reduction Act threatening to expand such incentives.

AI Summary. The U.S. financial system struggles to fund projects with long payback periods and modest returns, a category that includes major physical infrastructure such as factories and transmission lines. U.S. industrial policy also faces coordination failures and limited knowledge of the firms it aids, and relies on tax credits that are hard to repeal or adjust.

Date Posted:
Is Database:
Database

.@robinsonmeyer argues that Biden’s decarbonization based industrial policy faces three significant challenges: spending money efficiently, coordinating across multiple government agencies, and making policy adjustments over time.

.@robinsonmeyer argues that Biden’s decarbonization based industrial policy faces three significant challenges:...

Why does the U.S. struggle to finance long-payback infrastructure projects?

Core argument: The U.S. financial system persistently struggles to fund projects with long payback periods and modest returns, a category that includes the biggest and most important physical infrastructure, such as factories and transmission lines.

The U.S. financial system persistently struggles to fund projects that take a long time to turn a profit and that can expect to have only modest returns. Unfortunately, the biggest and most important physical infrastructure—factories, transmission lines—often fall under that category. Second, the government may lack the ability to coordinate its own actions. Late last year, the Biden administration declined to help reopen a “green” aluminum factory in Ferndale, Wash., that was exactly the kind of low-carbon industry it wants to champion. Never mind the right hand not knowing what the left hand is doing: The right hand couldn’t get the left hand to plug the cord in. Finally, the government may not understand enough about the companies it’s trying to help. In Taiwan and South Korea, industrial-policy agencies... constantly gather information from the private sector and use it to adjust goals and policies over time. The I.R.A.’s main incentives are tax credits, which are hard to repeal once they’re in place and hard to fix if they’re not working. They are an unusually mindless way to incentivize companies to change their behavior.

Takeaways by Macro Roundup® AI

  1. The U.S. financial system persistently struggles to fund projects with long payback periods and modest returns, a category that includes the biggest and most important physical infrastructure, such as factories and transmission lines.
  2. The Biden administration declined to help reopen a "green" aluminum factory in Ferndale, Wash., despite low-carbon industry being exactly the kind of sector it wants to champion, an example of the government's difficulty coordinating its own actions.
  3. The Inflation Reduction Act relies mainly on tax credits, which are hard to repeal once in place and hard to fix if they are not working, unlike industrial-policy agencies in Taiwan and South Korea that gather information from the private sector and adjust goals and policies over time.

Robinson Meyer argues that Biden’s decarbonization based industrial policy faces three significant headwinds: spending money efficiently, coordinating across multiple government agencies, and making policy adjustments over time. “The U.S. financial system persistently struggles to fund projects that take a long time to turn a profit and that can expect to have only modest returns. Unfortunately, the biggest and most important physical infrastructure — factories, transmission lines — often fall under that category. Second, the government may lack the ability to coordinate its own actions. Late last year, the Biden administration declined to help reopen a “green” aluminum factory in Ferndale, Wash., that was exactly the kind of low-carbon industry it wants to champion. Never mind the right hand not knowing what the left hand is doing: The right hand couldn’t get the left hand to plug the cord in. Finally, the government may not understand enough about the companies it’s trying to help. In Taiwan and South Korea, industrial-policy agencies… constantly gather information from the private sector and use it to adjust goals and policies over time. The I.R.A.’s main incentives are tax credits, which are hard to repeal once they’re in place and hard to fix if they’re not working. They are an unusually mindless way to incentivize companies to change their behavior.”

Robinson Meyer, “A Huge, Uncharted Experiment on the U.S. Economy Is About to Begin,” New York Times, February 12, 2023, https://www.nytimes.com/2023/02/12/opinion/economy-ira-infrastructure-clean-energy.html

A Huge, Uncharted Experiment on the U.S. Economy Is About to Begin

If you want to understand the immense windfall the Biden administration is about to bestow on green industries, take a look at hydrogen. Engineers still aren’t exactly sure what role the gas will play in a climate-friendly economy, but they’re pretty sure that (contra the ridicule in “Glass Onion”) it will be useful for something. We might burn it to generate heat in factories, for instance, or use it to make high-tech chemicals.

And thanks to three laws Congress passed over the past two years — the bipartisan infrastructure law, the CHIPS and Science Act and the climate-focused Inflation Reduction Act — the industry will be very well taken care of. Over the next decade, the government is going to invest $8 billion on hydrogen “hubs” across the country, special zones where companies, universities and local governments can build the machinery and expertise that the new industry needs. Other hydrogen projects will qualify for a $10 billion pot of money in the I.R.A. or $1.5 billion in the infrastructure bill. Still others could draw from a new $6.3 billion program that will help industrial firms develop financially risky demonstration projects.

So that’s up to $25.8 billion before you get to the bazooka: an uncapped tax credit for hydrogen that could pay out perhaps $100 billion or more over the next decades.

Few Americans realize it yet, but the trifecta of the Biden-era laws amounts to one of the biggest experiments in how the American government oversees the economy in a generation. If this experiment is successful, it will change how politicians think about managing the market for years to come. If it fails or misfires, then it will greatly limit the number of tools to fight climate change or a recession. The story of the 21st-century American economy is being shaped now.

I say “experiment,” but, really, there are two. The first concerns the economy. Mr. Biden’s team believes that it can move the United States toward a more robust, high-capacity and even re-industrialized economy. Can it? And can it use policy moreover to make sure that innovative ideas don’t get lost in the research lab or patent office, but instead make their way to the factory floor and corporate showroom, generating jobs and economic value along the way?

The second experiment: Can the same economy — which has, virtually since the abolition of slavery, derived a good deal of its industrial energy from extracting hydrocarbons from the ground and setting them on fire — find a new primary energy source? Even today, America generates 79 percent of its energy from fossil fuels. The administration is, in a sense, trying to conduct a high-stakes heart transplant on the economy while the patient remains alive on the table.

Don’t get me wrong: Some kind of climate boom is now all but assured. The investment bank Credit Suisse predicted last year that the I.R.A. would put more than $800 billion into the economy by the end of the decade, galvanizing more than $1.7 trillion in climate-friendly public and private spending overall. The law will transform the United States into the “world’s leading energy provider,” the bank said. The American renewable industry alone could attract 78 percent more investment per year by 2031, according to the energy-research firm Wood Mackenzie.

But I worry that the federal government has started its experiments too haphazardly. The I.R.A. did not emerge from careful study and bipartisan consensus building, but from intraparty haggling and a harried legislative process. Even the bipartisan CHIPS Act was more of a crisis measure than a strategic intervention. These shortcomings are forgivable; in the I.R.A.’s case, it’s not like Republicans were ever going to help pass a climate bill. But these constraints have deprived the government of the strong institutions, internal expertise and administrative capacity that have made similar experiments successful in other countries.

For practical purposes, that means, first, that the government won’t be able to spend all this money in the right place. The U.S. financial system persistently struggles to fund projects that take a long time to turn a profit and that can expect to have only modest returns. Unfortunately, the biggest and most important physical infrastructure — factories, transmission lines — often fall under that category. In other countries, industrial policy has entailed creating an agile, entrepreneurial agency that can get money to the right companies in the right ways — as a loan, as equity, as a purchase guarantee.

Congress took some steps in that direction last year. The I.R.A. beefed up the Loan Programs Office, the Department of Energy’s in-house bank, and it established a new green lending office within the Environmental Protection Agency. But Congress has put these institutions on a short leash with a limited mandate. This means that the government can’t support as many risky investments as it should.

Second, the government may lack the ability to coordinate its own actions. Late last year, the Biden administration declined to help reopen a “green” aluminum factory in Ferndale, Wash., that was exactly the kind of low-carbon industry it wants to champion. The local union, electric vehicle makers and the state’s Democratic leadership all wanted to revive the factory. The project even has national-security relevance, since the United States currently imports aluminum from Russia. But Mr. Biden chose not to intercede with the local electricity provider, the Bonneville Power Administration, to supply the plant with enough cheap power to operate even though it is a federal agency ostensibly under the president’s control. Never mind the right hand not knowing what the left hand is doing: The right hand couldn’t get the left hand to plug the cord in.

Finally, the government may not understand enough about the companies it’s trying to help. In Taiwan and South Korea, industrial-policy agencies don’t only hand out money; they constantly gather information from the private sector and use it to adjust goals and policies over time. The I.R.A. contains very few mechanisms for this kind of in-flight course adjustment. Its main incentives are tax credits, which are hard to repeal once they’re in place and hard to fix if they’re not working. They are an unusually mindless way to incentivize companies to change their behavior.

And this points to a related concern: that we have underestimated just how hard decarbonization will be. One of the most cherished and widely held ideas in climate activism is that we could have solved climate change by now if only we’d had the “political will.”

This idea, once true enough, may soon outlive its utility. Mr. Biden and his successors will discover that decarbonization is an inherently difficult and complex societal challenge that cannot be solved with money alone. Some important activities will be legitimately hard to do without emitting carbon pollution; there will be some trade-offs that flummox even the most committed progressives.

Which is to say: Even if the U.S. had an agency that could finance or approve any industrial project in the exact right way at the precise right time, it would still be legitimately unclear which projects it should support. Will a new lithium mine create jobs and build political support for decarbonization, or will its local pollution effects provoke backlash? If a new hydrogen hub opens in your hometown, will you love the growth or hate the higher housing costs?

The Biden experiments bear the mark of a particular set of lawmakers and White House staff members who needed to meet a particular set of goals. They sought to stimulate the pandemic-depleted economy, reduce carbon pollution in a durable way, respond to what they saw as the Chinese manufacturing juggernaut and — perhaps above all — revitalize the American working class to prevent the next Trumpian crisis. They stumbled on a germ of an idea, a climate-friendly “industrial strategy,” and after 18 months of excruciating legislative wrangling, they have somehow made it the law of the land.

But the lawmakers who wrote that policy are not charged with carrying it out, and many of the officials who championed it most — like Brian Deese, the director of the National Economic Council — are now leaving the White House. Will the next crew understand what they’ve inherited? In order for Mr. Biden’s two experiments to have a chance of success, the officials must not go on autopilot or disarm the parts of the I.R.A. meant to build domestic political support. And they cannot assume that everything about the coming climate boom will work out in the end. More than just the country’s fate depends on it.

AI Summary. Large U.S. infrastructure projects routinely exceed initial cost estimates and timelines: Honolulu's rail line, first estimated at $4bn, is projected at $11.4bn; California's high-speed rail has gone from $33bn to $100bn; and New York's East Side Access rose from $2.2bn to $11.1bn. Globally, 92% of such projects exceed original estimates.

Date Posted:
Is Database:
Database

US infrastructure projects have a history of significant cost overruns & delays, with 92% of global projects exceeding original estimates. Examples include Honolulu’s rail transit line & California’s high-speed rail.

Do large infrastructure projects routinely exceed their original cost estimates?

Core argument: Some 92% of global infrastructure projects exceed their original cost estimates, a pattern attributed to deceptive cost projections and systemic flaws in planning and budgeting.

The history of U.S. infrastructure projects is marked by significant cost overruns and delays, exemplified by Honolulu's rail transit line, initially estimated at $4bn in 2006, now projected to cost $11.4bn by 2031. Similarly, California's high-speed rail, intended to cost $33bn and complete by 2020, is now expected to finish in 2033 at $100bn. New York's East Side Access project saw costs rise from $2.2bn to $11.1bn over decades. These examples highlight systemic issues in planning and budgeting, with 92% of global projects exceeding original estimates due to deceptive cost projections. The $1.2tn infrastructure bill aims to address these challenges, but rising material costs and labor shortages pose risks to timely execution. The U.S. ranks 13th globally in infrastructure, with construction costs often surpassing those in Western Europe and Asia, underscoring the need for improved project management and transparency.

Takeaways by Macro Roundup® AI

  1. Some 92% of global infrastructure projects exceed their original cost estimates, a pattern attributed to deceptive cost projections and systemic flaws in planning and budgeting.
  2. Honolulu's rail transit line, estimated at $4bn in 2006, is now projected at $11.4bn by 2031, while California's high-speed rail has gone from $33bn and a 2020 completion to $100bn and 2033.
  3. The U.S. ranks 13th globally in infrastructure, with construction costs often exceeding those in Western Europe and Asia, and rising material costs and labor shortages pose risks to executing the $1.2tn infrastructure bill on time.

"... Honolulu... planners proposed an ambitious rail transit line that would sweep riders 20 miles into downtown. The $4 billion estimate in 2006 was hardly cheap, amounting to $200 million per mile. The launch dates slipped forward and the cost estimates crept upward — at latest count, $11.4 billion, with a target completion date of 2031..... When California voters approved a bond in 2008 for a high-speed rail system from Los Angeles to San Francisco, the project was supposed to cost $33 billion and be completed by 2020. The job is now projected to finish in 2033 for $100 billion, though those estimates are dated..... Lengthy delays have also affected New York’s East Side Access extension of the Long Island Rail Road. That project was supposed to be completed by 2011. Early estimates put the cost at $2.2 billion, then $4.3 billion in 2006 and $6.4 billion in 2008. The Metropolitan Transportation Authority now envisions completion in December 2022 at a cost of $11.1 billion....At the former Hanford nuclear weapons site in Washington State, the Energy Department announced a 17-year delay and estimated the system would become fully operational in 2036.The last cost estimate for the plant was $17 billion, up from $12.3 billion in 2013 and about $4 billion 20 years ago.... tribulations are far from a lone cautionary tale. To the contrary, they signal the kind of cost overruns, engineering challenges and political obstacles that have made it all but impossible to complete a major, multibillion-dollar infrastructure project in the United States on budget and on schedule....Bent Flyvbjerg, a professor at the University of Oxford who has studied scores of projects around the world, found that 92 percent of them overran their original cost and schedule estimates, often by large margins — in part, he said, because cost estimates are “systematically and significantly deceptive.”...Setbacks that resulted in delays... plague nearly all major infrastructure projects; the common mistake is in not planning and budgeting for them, said Joseph Schofer, a Northwestern University civil engineer and originator of the “Infrastructure Show” podcast. "We haven’t gotten honest estimates in a lot of cases.”... In a candid admission of how the political world operates, Willie Brown, the former mayor of San Francisco, once dismissed cost overruns on a transportation hub intended for the bullet train.....“In the world of civic projects, the first budget is really just a down payment,” he wrote in a guest newspaper column in 2013. “If people knew the real cost from the start, nothing would ever be approved. The idea is to get going. Start digging a hole and make it so big there’s no alternative to coming up with the money to fill it in.”..."

Ralph Vartabedian, "Years of Delays, Billions in Overruns: The Dismal History of Big Infrastructure,"New York Times, November 28, 2021, https://www.nytimes.com/2021/11/28/us/infrastructure-megaprojects.html

Years of Delays, Billions in Overruns: The Dismal History of Big Infrastructure

As Honolulu sprawled into new suburbs west of Pearl Harbor over the last two decades, city planners proposed an ambitious rail transit line that would sweep riders 20 miles into downtown. The $4 billion estimate in 2006 was hardly cheap, amounting to $200 million per mile.

The cost escalation since then has been an engineering marvel all its own. Concerns over Native Hawaiian burial grounds stalled early construction, then problems with welding and cracks in the tracks appeared. Earlier this year, engineers realized that in some sections, the wheels were a half-inch narrower than the rails. Order new wheels? Tear up the tracks?

The launch dates slipped forward and the cost estimates crept upward — at latest count, $11.4 billion, with a target completion date of 2031.

Honolulu’s tribulations are far from a lone cautionary tale. To the contrary, they signal the kind of cost overruns, engineering challenges and political obstacles that have made it all but impossible to complete a major, multibillion-dollar infrastructure project in the United States on budget and on schedule over the past decade.

As the nation sets out on a national spending spree fueled by the $1.2 trillion infrastructure bill signed by President Biden this month, the job ahead carries enormous risks that the projects will face the same kind of cost, schedule and technical problems that have hobbled ambitious efforts from New York to Seattle, delaying benefits to the public and driving up the price tag that taxpayers ultimately will bear.

American cities and states were long renowned for some of the greatest bridges, water systems and freeways in the world, but challenges have grown more potent. Agencies have less internal technical talent. Legal challenges have grown stronger under state and federal environmental laws. And spending on infrastructure as a fraction of the economy has shrunk, giving local agencies less experience in modern practices.

The $1.2 trillion package has bold goals, directing the majority of $500 billion to highways, $39 billion to urban transit, $65 billion to broadband projects and $73 billion to electrical grids, among other items. The nation’s busiest passenger rail line, Amtrak’s Boston-to-Washington corridor, would get the biggest slice of a $66 billion rail package. The infrastructure spending plan is unlikely to rescue some existing infrastructure projects that are bogged down with problems.

And even with the new infusion of money, analysts say it will be tough to ramp up infrastructure progress as swiftly as envisioned in the current timetable.

The construction industry is facing sharply growing costs for steel products, up by 142 percent in the last 12 months, and other key materials. Shortages of skilled labor are worsening, exacerbated by Covid-induced retirements.

“A lot of people would like to see the money quickly spent,” said Anirban Basu, chief economist of Associated Builders and Contractors, a construction industry trade group. “They are going to look at the costs they are facing and extend out the projects because of constraints.”

Bent Flyvbjerg, a professor at the University of Oxford who has studied scores of projects around the world, found that 92 percent of them overran their original cost and schedule estimates, often by large margins — in part, he said, because cost estimates are “systematically and significantly deceptive.”

“A lot of projects are not delivering what they promised to deliver,” he said.

In Baltimore this month, Mr. Biden lamented that U.S. infrastructure was once rated the world’s best and now, “You know what we rank in infrastructure? Thirteenth in the world.”

In some cases, U.S. construction costs are higher than those in Western Europe and democratic nations in Asia, according to an upcoming University of California, Berkeley, analysis, said Ethan Elkind, a law professor and director of the school’s climate program.

“It is a lot harder to build projects here, and we are not as skilled at doing it,” he said.

When California voters approved a bond in 2008 for a high-speed rail system from Los Angeles to San Francisco, the project was supposed to cost $33 billion and be completed by 2020. The job is now projected to finish in 2033 for $100 billion, though those estimates are dated and there is an $80 billion funding gap.

The ambitious project, the nation’s most serious effort to build a full-scale bullet train, has encountered serious delays because of land acquisition issues, environmental litigation, permit setbacks, employee turnover and significant design changes. The problems have triggered political infighting even with the Democratic supermajority in California.

Lengthy delays have also affected New York’s East Side Access extension of the Long Island Rail Road, which is supposed to cut up to 40 minutes off commuter time on the last segment, from Queens to Grand Central Terminal, with up to 24 trains per hour at peak times.

Conceived more than a half century ago, with a construction contract awarded in 2006, that project was supposed to be completed by 2011. Early estimates put the cost at $2.2 billion, then $4.3 billion in 2006 and $6.4 billion in 2008. The Metropolitan Transportation Authority now envisions completion in December 2022 at a cost of $11.1 billion. Design changes, underground tunneling problems and coordination with other agencies were some of the factors in the delays and cost increases.

One of the nation’s most important environmental infrastructure projects, and perhaps the most technically difficult one, has been underway in Central Washington State for decades at the former Hanford nuclear weapons site. Since 2013, major construction has been stopped at two partially built plants to treat and vitrify 56 million gallons of radioactive sludge.

When an independent review in 2015 found 362 significant design problems, the Energy Department announced a 17-year delay and estimated the system would become fully operational in 2036.

The problems included the failure to anticipate the potential for an earthquake to damage equipment and the possibility that the chemical processes to separate high-level radioactive materials could cause explosive hydrogen gas to form.

The delays have pushed the Energy Department to adopt an alternative that would start treating low-level waste by the end of 2023, Washington State officials said. The last cost estimate for the plant was $17 billion, up from $12.3 billion in 2013 and about $4 billion 20 years ago.

The rail project in Hawaii was intended to relieve congestion on a par with Los Angeles along the urban band from East Kapolei to the core of Honolulu.

The Honolulu Authority for Rapid Transportation believes it can address the latest track problems by welding certain sections of track and later replacing wheels to match the track size, said a spokesman, Harry Cho.

The setbacks that resulted in delays — archaeological surveys, labor costs, utility relocations and land acquisition — are the kind of challenges that plague nearly all major infrastructure projects; the common mistake is in not planning and budgeting for them, said Joseph Schofer, a Northwestern University civil engineer and originator of the “Infrastructure Show” podcast.

“You can’t say these were an accident,” he said of most cost overruns. “We could do better. We haven’t gotten honest estimates in a lot of cases.”

Mr. Schofer said many projects are justified by estimating that future benefits will exceed costs, but when the costs go up astronomically, no one recalculates the ratio.

In a candid admission of how the political world operates, Willie Brown, the former mayor of San Francisco, once dismissed cost overruns on a transportation hub intended for the bullet train.

“In the world of civic projects, the first budget is really just a down payment,” he wrote in a guest newspaper column in 2013. “If people knew the real cost from the start, nothing would ever be approved. The idea is to get going. Start digging a hole and make it so big there’s no alternative to coming up with the money to fill it in.”

U.S. Transportation Department officials declined to comment for this article, but Biden administration officials have said the new infrastructure package will redress decades of neglect and will boost the efficiency of the American economy, address climate change and provide immediate jobs in construction.

“We’re going to reduce congestion,” Mr. Biden said. “We’re going to address repair and maintenance backlogs, deploy state-of-the-art technologies and make our ports cleaner and more efficient.”

Mr. Flyvbjerg, the Oxford professor, said infrastructure keeps getting more expensive at a time when many products, such as televisions, refrigerators and computers, get cheaper or better each year.

“Big infrastructure is becoming cost prohibitive,” he said, a problem he blames on institutional sclerosis at government agencies that keep repeating mistakes and choose infrastructure projects that are unlikely to succeed.

The mistakes, he said, include a lack of transparency to the public, flawed contracts that put government agencies at the mercy of contractors and a failure to attract enough private investment to bear some of the project’s risk.

The new infrastructure law, he said, does little to change the outlook.

Ronald N. Tutor, chief executive of Tutor Perini, a California firm that is building some of the nation’s largest projects, said the industry has done a good job of advancing and completing projects that by their nature are complex and unpredictable.

“All the major projects have cost and schedule issues,” he acknowledged. “The truth is these are very high-risk and difficult projects. Conditions change. It is impossible to estimate it accurately. That is naïve.”

The infrastructure law takes some initial steps at reforms, including codifying a Trump executive order to name a lead federal agency for each project, reducing the number of chefs in the kitchen, said Diana Furchtgott-Roth, who formerly oversaw Transportation Department research and technology and now is a George Washington University adjunct professor.

A key factor is the amount of time federal agencies spend to review environmental reports and issue records of decision, she said. In many cases, she said, projects are put on hold for years, while agencies review voluminous documents.

Mr. Biden also named a task force to carry out the infrastructure program with an aim to “invest public dollars efficiently, avoid waste and focus on measurable outcomes for the American people.”

The environmental review process has become so complex, in part to defend against inevitable lawsuits, that neither state agencies nor federal departments can write and review the documents without teams of outside consultants.

Most of the spending under the $1.2 trillion infrastructure plan has been previously authorized, but the law includes $550 billion of new money to be spent in as little as five years.

Federal, state and local agencies were working their way through $270 billion a year in authorized spending in 2019, before the pandemic hit. An attempt to bump that up by an additional $100 billion annually, as envisioned, represents a 37 percent jump that may not be possible to achieve, industry analysts warn.

“It is a very big bump,” said Ken Simonson, chief economist at Associated General Contractors of America, which represents major infrastructure builders. “My guess is that we are not going to see $550 billion spent in the first five years.”

AI Summary. A shortage of skilled construction labor poses a challenge to large-scale U.S. infrastructure spending, with only 10% of infrastructure workers under 25 versus 13% of all U.S. workers and a median age of 53 for construction and building inspectors. The construction industry faces a projected shortfall of 2m workers, and 88% of contractors report difficulty finding skilled labor.

Date Posted:
Is Database:
Database

Labor shortage threatens Biden’s $1.4tn infrastructure plan: With a skilled worker gap and only 10% under age 25, construction faces a 2m-worker shortfall by 2025, risking delays in critical projects.

Does a shortage of skilled construction workers threaten large infrastructure spending?

Core argument: Only 10% of U.S. infrastructure workers are under 25, versus 13% of all U.S. workers, and the median age of construction and building inspectors is 53 against 42.5 nationwide.

The scarcity of skilled workers poses a significant challenge to President Biden's infrastructure plan, as only 10% of infrastructure workers are under 25, compared to 13% of all U.S. workers, highlighting a generational gap in the workforce. This shortage is exacerbated by the aging workforce, with the median age of construction and building inspectors at 53, compared to 42.5 for all workers nationwide. The construction industry faces a potential shortfall of 2m workers by 2025, with 88% of contractors reporting difficulty finding skilled labor. Despite competitive wages, younger generations often pursue college degrees over trade careers, further limiting the pool of available workers. The infrastructure bill aims to create millions of jobs, but without sufficient labor, projects may be delayed, impacting economic growth and productivity gains estimated at $1.4tn over eight years. Addressing this gap requires targeted workforce development and training initiatives to attract younger workers into these critical sectors.

Takeaways by Macro Roundup® AI

  1. Only 10% of U.S. infrastructure workers are under 25, versus 13% of all U.S. workers, and the median age of construction and building inspectors is 53 against 42.5 nationwide.
  2. The construction industry faces a potential shortfall of 2m workers by 2025, with 88% of contractors reporting difficulty finding skilled labor.
  3. Insufficient labor may delay infrastructure projects, affecting economic growth and productivity gains estimated at $1.4tn over eight years, and closing the gap requires targeted workforce development and training initiatives.

Properly trained talent as a potential limiting constraint to infrastructure, “…The issue underscores a perennial challenge for the skilled trades. Not enough young people are entering the sectors, a concern for companies as older workers retire from construction, carpentry and plumbing jobs. And although many skilled trade positions have competitive wages and lower educational barriers to entry, newer generations tend to see a four-year college degree as the default path to success. Infrastructure workers tend to be older than average, raising concerns about workers retiring and leaving behind difficult-to-fill positions. The median age of construction and building inspectors, for instance, is 53, compared with 42.5 for all workers nationwide. Only 10 percent of infrastructure workers are under 25, while 13 percent of all U.S. workers are in that age group, according to a Brookings Institution analysis…. Nicholas Kadavy, a third-generation mason who owns Nebraska Masonry in Lincoln, Neb., has seen his workload triple since April. He said his company had already scheduled out work until June 2022. He wants to hire more skilled masons to finish the projects sooner, but he can’t find enough people to fill the dozen positions he has open, even though he is willing to pay up to $50 an hour — twice what he offered before the pandemic. He checks his email daily, waiting for more applications to come in. “My biggest struggle is finding guys that want to work,” Mr. Kadavy said. Even when he does hear from applicants, Mr. Kadavy said, he is unable to hire many of them because they are not qualified enough. He was already seeing a shortage of skilled masons before the pandemic, he said, and he worries that the craft is “dying” because newer generations are not pursuing the field. The nation’s public transit systems would receive $39 billion under the infrastructure bill, allowing agencies to expand service and upgrade decades-old infrastructure. But transit agencies are dealing with worker shortages of their own, facing a dearth of bus drivers, subway operators and maintenance technicians. Metro Transit in Minneapolis is trying to hire about 100 bus drivers by the end of the year, said Brian Funk, the agency’s acting chief operating officer. The agency had originally aimed to hire 70 workers by the end of June, but it met only about half of that goal….”

Madeleine Ngo, "Skilled Workers Are Scarce, Posing a Challenge for Biden’s Infrastructure Plan,"New York Times, September 12, 2021, https://www.nytimes.com/2021/09/09/us/politics/biden-infrastructure-plan.html

Skilled Workers Are Scarce, Posing a Challenge for Biden’s Infrastructure Plan

WASHINGTON — The infrastructure bill that President Biden hopes to get through Congress is supposed to create jobs and spur projects for companies like Anchor Construction, which specializes in repairing aging bridges and roadways in the nation’s capital.

But with baby boomers aging out of the work force and not enough young people to replace them, John M. Irvine, a senior vice president at Anchor, worries there will not be enough workers to hire for all those new projects.

“I’d be surprised if there’s any firm out there saying they’re ready for this,” said Mr. Irvine, whose company is hiring about a dozen skilled laborers, pipe layers and concrete finishers. If the bill passes Congress, he said, the company will most likely have to double the amount it is hiring.

“We will have to staff up,” Mr. Irvine said. “And no, there are not enough skilled workers to fill these jobs.”

Mr. Biden has hailed the $1 trillion infrastructure bill as a way to create millions of jobs, but as the country faces a dire shortage of skilled workers, researchers and economists say companies may find it difficult to fill all of those positions.

The bill could generate new jobs in industries critical to keeping the nation’s public works systems running, such as construction, transportation and energy. S&P Global Ratings estimated that the bill would lift productivity and economic growth, adding $1.4 trillion to the U.S. economy over eight years. But if there is not enough labor to keep up with the demand, efforts to strengthen the nation’s highways, bridges and public transit could be set back.

“Do we have the work force ready right now to take care of this? Absolutely not,” said Beverly Scott, the vice chair of the President’s National Infrastructure Advisory Council.

A recent U.S. Chamber of Commerce survey found that 88 percent of commercial construction contractors reported moderate-to-high levels of difficulty finding skilled workers, and more than a third had to turn down work because of labor deficiencies. The industry could face a shortage of at least two million workers through 2025, according to an estimate from Construction Industry Resources, a data firm in Kentucky.

The pandemic has compounded labor shortages, as sectors like construction see a boom in home projects with more people teleworking and moving to the suburbs. Contractors have also faced a scarcity of supplies as prices soared for products like lumber and steel.

Job openings in construction have picked up at a rapid clip after the sector lost more than one million jobs at the beginning of the pandemic. According to an Associated Builders and Contractors analysis, construction job openings have increased by 12 percent from prepandemic levels. But the sector is still down about 232,000 jobs from February 2020, according to data from the Bureau of Labor Statistics.

The issue underscores a perennial challenge for the skilled trades. Not enough young people are entering the sectors, a concern for companies as older workers retire from construction, carpentry and plumbing jobs. And although many skilled trade positions have competitive wages and lower educational barriers to entry, newer generations tend to see a four-year college degree as the default path to success.

Infrastructure workers tend to be older than average, raising concerns about workers retiring and leaving behind difficult-to-fill positions. The median age of construction and building inspectors, for instance, is 53, compared with 42.5 for all workers nationwide. Only 10 percent of infrastructure workers are under 25, while 13 percent of all U.S. workers are in that age group, according to a Brookings Institution analysis.

“The challenge is, how are we going to replace — not just grow, but replace — many of the workers who are retiring or leaving jobs?” said Joseph W. Kane, a fellow at the Brookings Institution. “A lot of people, especially younger people, just aren’t even aware that these jobs exist.”

Community colleges, which offer a variety of vocational training programs, have suffered steep declines in enrollment. A recent estimate from the National Student Clearinghouse Research Center found that community colleges were the hardest hit among all colleges, with enrollment declining by 9.5 percent this spring. More than 65 percent of the total undergraduate enrollment losses this spring occurred at community colleges, according to the report.

Nicholas Kadavy, a third-generation mason who owns Nebraska Masonry in Lincoln, Neb., has seen his workload triple since April. He said his company had already scheduled out work until June 2022.

He wants to hire more skilled masons to finish the projects sooner, but he can’t find enough people to fill the dozen positions he has open, even though he is willing to pay up to $50 an hour — twice what he offered before the pandemic. He checks his email daily, waiting for more applications to come in.

“My biggest struggle is finding guys that want to work,” Mr. Kadavy said.

Even when he does hear from applicants, Mr. Kadavy said, he is unable to hire many of them because they are not qualified enough. He was already seeing a shortage of skilled masons before the pandemic, he said, and he worries that the craft is “dying” because newer generations are not pursuing the field.

The nation’s public transit systems would receive $39 billion under the infrastructure bill, allowing agencies to expand service and upgrade decades-old infrastructure. But transit agencies are dealing with worker shortages of their own, facing a dearth of bus drivers, subway operators and maintenance technicians.

Metro Transit in Minneapolis is trying to hire about 100 bus drivers by the end of the year, said Brian Funk, the agency’s acting chief operating officer. The agency had originally aimed to hire 70 workers by the end of June, but it met only about half of that goal.

Although he is optimistic that the agency will be able to fill those remaining positions after ramping up efforts to promote the openings, he said he was still wary about some workers choosing to leave.

“We know that every day that goes by, there’s the potential that somebody else is looking at either retirement or another job,” Mr. Funk said.

Some are optimistic that policymakers will be able to scale up work force development programs to keep up with the demand the infrastructure bill would create. Projects could take several months to get started, economists said, giving the country time to train workers who are not yet qualified.

“These problems are not insurmountable,” said Nicole Smith, the chief economist at the Georgetown University Center on Education and the Workforce. “Not having a sufficiently trained work force is something that can be addressed.”

But others are worried that the bill does not do enough to draw more people into infrastructure fields, especially historically underrepresented groups like women and people of color. Although Mr. Biden originally proposed a $100 billion investment in work force development, that funding was left out in the latest version of the bipartisan infrastructure bill. The funding would have invested in job training for formerly incarcerated people and created millions of registered apprenticeships, among other things.

Last week, the National Skills Coalition and more than 500 other organizations sent a letter to congressional leadership calling on it to include the funding in a separate reconciliation bill.

“President Biden promised that economic recovery was going to be predicated on equity,” said Andy Van Kleunen, the chief executive of the National Skills Coalition. “Work force training has to be part of that answer.”

AI Summary. Federal highway grants under the 2009 US Recovery Act raised state highway spending by only about 19 cents per dollar, with states cutting their own contributions by roughly 81 cents per federal dollar amid recession-driven budget stress. The share of structurally deficient or functionally obsolete bridges moved little, from 26.9% to 25.4%.

Date Posted:
Is Database:
Database

@BillDupor, the 2009 Recovery Act’s federal highway funds failed to enhance the nation’s infrastructure due to states substituting federal dollars for their own spending, with each grant dollar resulting in a state cut of 81 cents.

Do federal highway grants raise total state highway spending?

Core argument: Statistical analysis indicates each federal highway grant dollar from the 2009 Recovery Act raised state highway spending by only 19 cents, with states cutting their own contributions by 81 cents per federal dollar received.

The 2009 Recovery Act's federal highway funds failed to enhance the nation's infrastructure due to states substituting federal dollars for their own spending. Despite a significant influx of federal funds, the percentage of structurally deficient or functionally obsolete bridges barely changed from 26.9% in 2008 to 25.4% in 2011. Statistical analysis reveals that each federal grant dollar increased state highway spending by only 19 cents, indicating substantial crowding out, as states cut their own contributions by 81 cents per federal dollar received. This fiscal substitution was driven by states reallocating funds to other areas amid budget stress from declining tax revenues during the recession. Consequently, over 40% of the U.S. population resided in states where total highway construction spending decreased post-2008, highlighting the limited impact of the Recovery Act on improving highways and bridges.

Takeaways by Macro Roundup® AI

  1. Statistical analysis indicates each federal highway grant dollar from the 2009 Recovery Act raised state highway spending by only 19 cents, with states cutting their own contributions by 81 cents per federal dollar received.
  2. The share of U.S. bridges rated structurally deficient or functionally obsolete moved only from 26.9% in 2008 to 25.4% in 2011, despite a large influx of federal highway funds.
  3. Over 40% of the U.S. population lived in states where total highway construction spending declined after 2008, amid budget stress from declining tax revenues.

When states get federal highway dollars they substitute those for their own highway spending. The Recovery act from the last recession, therefore, didn’t improve highways much because the level of spending stayed roughly constant. Bill Dupor reports the 2009 Federal stimulus money had no net impact on highway infrastructure as states used the Federal dollars to offset their own existing highway spending, "...I first show that, despite the tremendous influx of federal funds, the highway system showed little improvement. For example, in 2008, 26.9 percent of the nation’s bridges were classified as either structurally deficient or functionally obsolete. In 2011, this percentage was nearly unchanged at 25.4 percent. In the three years following passage of the Recovery Act, the number of workers on federal-aid highway projects changed only negligibly. Moreover, over 40 percent of the U.S. population lived in states where highway construction spending, from all sources, was lower in 2010 (post-passage) than in 2008 (pre-passage). Over the same time, many of these states increased spending on some non-transportation items. Although the act specified that the highway funds be put to specific use, it is important to recognize that state governments were already spending significant amounts of their own dollars on highways—for example, $50.1 billion in 2008. Upon receipt of new federal funds, states could potentially cut their own contributions to highway capital spending which, in turn, would free up those funds for other uses.Since states were facing budget stress from declining tax revenues resulting from the recession, it stands to reason that states had the incentive to do so. I also explain how the language of the act made it possible for many state government officials to cut states’ own spending on highways upon receipt of Recovery Act dollars. In fact, 15 states cut their total highway capital spending (i.e., from all sources) between 2008 and 2010, freeing up their own funds for other uses. Second, I estimate the grants’ effect on highway spending. That is, how much did the grants increase highway infrastructure investment relative to a no-stimulus baseline? I conduct statistical tests, which deliver results consistent with federal aid “crowding out” state spending. Specifically, I run cross-sectional, state-level regressions of per capita Recovery Act FHWA dollars on the post-enactment change in per capita highway infrastructure spending. If there is no crowding out—that is, fiscal substitution—then one would expect a one-for-one dollar increase in highway spending when a state received FHWA Recovery Act grants. I do not find a one-for-one response. Instead, I find that there is no statistically significant effect of FHWA Recovery Act grants on state highway infrastructure spending. In my benchmark specification, a point estimate indicates that each Recovery Act FHWA grant dollar increased states’ highway spending by 19 cents. This qualitative finding is robust to a large set of alternative specifications. Thus, the fiscal substitution hypothesis is able to explain why there was little impact on the nation’s highways and bridges following the passage of the Recovery Act. Stated simply, highway infrastructure spending without the act would not have been very different relative to what was actually observed in absence of the act...."

"... Table 2 contains my benchmark finding. The coefficient on Recovery Act FHWA obligations equals 0.19 (0.43 standard error; Column 1). The point estimate implies that, in per capita terms, one additional grant dollar to a state causes 19 cents of additional highway infrastructure in that state. This represents substantial crowding out of state contributions to highways. For each grant dollar, the state government cuts its own contribution to highway infrastructure by 81 centsThe log of population is an important predictor of state per capita highway spending. The coefficient is negative, so higher-population states experienced relatively less additional highway spending (per capita) in 2009 and 2010. Moreover, the coefficient is statistically different from zero at a 95 percent confidence level. While I include a population measure in the regression, in a related study, Leduc and Wilson (forthcoming) estimate a similar regression but do not include a population control. They find little evidence of crowding out, with their analogous coefficient greater than 1. The difference between my study and theirs is likely due the absence of a population control in their regression, although there are other differences across the two papers’ specifications as well…”

So, Why Didn't the 2009 Recovery Act Improve the Nation's Highways and Bridges?: Extended Excerpt Image 1


“…Column 2 of the table presents results when obligations are replaced with outlays. The results are qualitatively unchanged. There is no statistically significant effect of Recovery Act highway grants on the change in state highway spending; and, moreover, the coefficient on the population measure is negative and statistically different from zero. Columns 3 and 4 of the table provide identical specifications to those in the first two columns, except I weight the regression by the natural log of the population. Again, the results are qualitatively unchanged. Moreover, this estimate is not statistically different from zero. As such, I cannot reject the hypothesis of a complete crowding out of state highway spending by Recovery Act highway funds….”

".. Figure 5 represents the paper’s main finding graphically. It contains a scatter plot where each point corresponds to a state, with the Recovery Act FHWA obligations per capita (after controlling for log population) on the horizontal axis and the accumulated per capita change in highway spending on the vertical axis. Note that there is little discernable positive or negative correlation in the data. If there were no crowding out (i.e., each grant dollar was spent on highways) and no other disturbances, then the points would lie on the 45-degree line. The solid line indicates the best linear fit of the data, with the slope equal to the coefficient a. The shaded region is the 90 percent confidence interval. Since the coefficient is not statistically different from zero, this region contains a flat response of grant obligations to highway infrastructure spending..."

So, Why Didn't the 2009 Recovery Act Improve the Nation's Highways and Bridges?: Extended Excerpt Image 2


Bill Dupor, "So, Why Didn't the 2009 Recovery Act Improve the Nation's Highways and Bridges?," Social Science Research Network, May 20, 2021, https://papers.ssrn.com/sol3/papers.cfm

Ed Comment: So typical. At Bain, we called this pushing on a balloon. Things are more likely to move around than to increase or decrease. Unfortunately, the public sector is largely unsupervised and poorly supervised when it is. Tough/effective supervision makes sure you’re not just pushing on a balloon.

AI Summary. US infrastructure projects cost more than international counterparts, averaging $1,601m per mile versus a global average of $478m, with a median of $965m per mile compared with $299m outside the US. Contributing factors include complex project designs, regulatory delays, elevated labor costs, and procurement and project management inefficiencies, while land costs are a minor component.

Date Posted:
Is Database:
Database

US infrastructure projects are expensive, with average costs reaching $1,601m per mile, compared to a global average of $478m. Complex designs, regulatory delays, and high labor costs contribute to these high costs. @EdwardGlaeser

Why do US infrastructure projects cost so much more than abroad?

Core argument: US infrastructure projects average $1,601m per mile against a global average of $478m, with the median US project at $965m per mile versus a non-US median of $299m.

US infrastructure projects are notably more expensive than international counterparts, with average costs reaching $1,601m per mile compared to a global average of $478m. The median US project costs $965m per mile, significantly higher than the non-US median of $299m. Factors contributing to these high costs include complex project designs, regulatory delays, and elevated labor costs, such as electricians in NYC earning a median hourly wage of $36.13, with project-specific rates reaching $65 plus benefits. Despite high real estate prices, land costs are a minor component. The inefficiencies in procurement and project management further exacerbate expenses. Addressing these issues could optimize infrastructure budgets and improve cost-effectiveness.

Takeaways by Macro Roundup® AI

  1. US infrastructure projects average $1,601m per mile against a global average of $478m, with the median US project at $965m per mile versus a non-US median of $299m.
  2. Complex project designs, regulatory delays, and elevated labor costs contribute to US infrastructure expenses, with NYC electricians earning a median hourly wage of $36.13 and project-specific rates reaching $65 plus benefits.
  3. Land costs are a minor component of US infrastructure spending despite high real estate prices, while procurement and project management inefficiencies add to expenses.

Edward Glaeser, and James Poterba take the lay of the land on America's infrastructure, their bottom line, "...Our assessment of the role of economic analysis in infrastructure investment suggests several broad conclusions. First, it is difficult to place high confidence in widely discussed measures of infrastructure “need.” The most reliable way to develop such estimates would be by applying cost-benefit analysis on a project-by-project basis and aggregating the results. But that approach is expensive, given the vast array of potential infrastructure projects, and it is subject to gaming by overstating future benefits and low-balling costs. Estimates of the returns to maintaining existing infrastructure are often higher than estimates of the returns to undertaking new projects, which suggests the importance of guarding against “ribbon-cutting bias” toward new initiatives on the part of both elected leaders and the heads of government agencies. Any major infrastructure initiative should emphasize careful ex ante analysis of project costs and benefits, with oversight where feasible of padding by advocates of the assumptions regarding future costs and benefits. Second, infrastructure projects in the United States are expensive relative to those in other nations. The precise reasons are difficult to identify, but they include project designs that incorporate many features that remediate adverse project effects, such as highway noise and the inconvenience of disruption while building, required wages for workers that may exceed area norms, project delay through regulatory processes, and weak procurement and project management by the relevant government agencies.Third, user fees warrant greater consideration as a source of infrastructure project financing. Such fees, along with congestion charges, can improve the efficiency of infrastructure use. While there are concerns about the distributional effects of user fees and burdens on low-income groups in particular, the pattern of infrastructure use across income groups suggest that some user fees are progressive—higher income households use airports, for example, more than their lower income counterparts. Public transit, particularly buses, is a notable exception. Rather than carry out income redistribution by exempting infrastructure use from charges, policymakers could consider targeted redistribution programs, such as transit vouchers for low-income households or infrastructure-use rebates mediated through the tax system. Some states currently provide income tax relief for renters or for commuters who can document their travel costs. Finally, public-private partnerships can provide a means to increase operational efficiency, but arguments that they allow project sponsors to access low-cost capital should be viewed with caution. In some cases, the cost of capital for private entities may exceed that for public sector borrowers and relying on private finance rather than public funding may ultimately increase the 42 cost of the project. Some state and local governments may be attracted to these partnerships because they relieve current cash flow constraints, but they may come at a price in terms of the long-term cost of infrastructure services...."

Economic Perspectives on Infrastructure Investment: Extended Excerpt Image 1

Edward Glaeser, and James Poterba, "Economic Perspectives on Infrastructure Investment," Aspen Economic Strategy Group, July 14, 2021, https://www.economicstrategygroup.org/publication/poterba-glaeser-infrastructure-investment/

Evidence:“…Flyvbjerg, Bruzelius, and van Wee (2008) compare the capital costs for urban rail projects around the world. The costs for the six systems in the United States that were included in the analysis range from $88 million per kilometer (Atlanta) to $147.5 million per kilometer (Baltimore). Thirteen out of 17 of the European systems in the study, and five out of six in Asia or Latin America, had costs below $88 million per kilometer. Levy (2011) argues that these comparisons understate the cost disadvantage of U.S. projects, noting that “the American projects examined are quite old, from the 1980s, and many have large above-ground parts.” He further identifies three New York City projects with costs of $1.3 billion, $1.7 billion, and $4 billion per km, as well as San Francisco’s Central Subway, which cost $500 million per kilometer even though, as a light rail tunnel, it was a less demanding project. Levy’s updated Transit Cost database reports actual or projected cost-per-kilometer data, converted to $US using purchasing power parity exchange rates, on 540 different projects, including 256 that were completed by 2020. We inflation-adjust these cost estimates using the CPI and assume that the median dollar was spent in the year that was half-way between the start and end date of the project. We treat projects with average years beyond 2021 as having an average year of 2021. 7 Table 4 presents our findings.For the 19 projects in the database that are in the United States, the average cost was $1,601 million per mile, compared with a non-U.S. global average of $478 million. The median U.S. project was $965 million per mile, compared with a non-U.S. median of $299 million. The database also contains information on the share of the rail system that is underground. When we restrict our analysis to the 255 projects that are 100% in tunnels, the median cost of the 11 U.S. projects is $1,379 million per mile, compared with a non-U.S. global median of $341 million. While precise comparisons are difficult, many projects in densely populated foreign cities have substantially lower per-mile costs than their U.S. counterpartsThe cost breakdown highlights a number of important patterns. First, real estate costs are a tiny share of the project’s total cost, despite New York City’s sky-high property prices. Second, neither administrative and regulatory costs, nor the even smaller category of environmental mitigation (contained within construction and only $2.14 million) were significant causes of the high costs. Third, the two largest elements in construction costs were tunneling ($3.1 billion) and stations and intermodal facilities ($2.3 billion). The very expensive station construction is one reason why East Side Access was the most expensive project in the database,but the tunneling on its own is extraordinarily costly by global standards. While direct environmental mitigation itself was a small component of the accounting costs, environmental factors play a much larger role in the overall cost of the project by changing the nature of construction itself. For example, BVP (2018) explain that “the Environmental Impact Statement (EIS) required construction activities in Manhattan to take place in the subterranean realm, with almost all equipment and spoils transitioning through the 63rd Street tunnels to staging sites in Sunnyside Yards,” which typically meant “laborers filling burlap bags with spoils that were then loaded onto trains to Queens (or in some cases, the Bronx) and then unloaded and sorted by laborers.” The Metropolitan Transit Authority (MTA) estimated that it could have saved $75 million in schedule-related costs alone by deploying a simpler system similar to that used in other projects…Arguably, the conditions for tunneling in Manhattan are as difficult as anywhere in the world, although cost estimates for projects in London, which are all completely underground, are only one-third as high as those in New York City. Labor costs are higher in the United States than elsewhere, and especially so in New York City, but this reflects institutions as well as generally high labor costs. The Bureau of Labor Statistics (BLS) reports that in May 2020, the median hourly wage for electricians in the New York City metropolitan area was $36.13, and the mean was $40.48.9 BVP (2018) report a minimum hourly wage for electricians of $65 on the East Side Access project and an added $62 dollars per hour in benefits, making the per-unit labor cost for the project a multiple of the prevailing wage….”

Why does it cost so much to build infrastructure in the U.S.?“…Beyond accounting, there are three deeper explanations for why infrastructure costs are so high in the United States. First, it is possible that conditions are more demanding and that raw materials and labor are more expensive than elsewhere. This explanation suggests that higher costs are unavoidable but should be considered in discussions of optimal infrastructure policy, since higher costs are a good reason to build less infrastructure. Second, it is possible that the agencies charged with building infrastructure are poorly designed to manage costs. In this case, there may be changes to infrastructure building practices that could lower costs and stretch infrastructure budgets. Third, it is possible that external factors, especially the threat of litigation or political backlash, lead to expensive forms of mitigation, which change the nature and cost of building projects(Altshuler and Luberoff 2005)…”